I received an anonymous change proposal for this site with the following updates:
350kW connectors from 1 to 2
150kW connectors from 3 to 4
Change provider from Electrify America to EVolveNY
In case the anonymous proposer reads this, I will offer an explanation as to why I will be rejecting all 3 proposals.
While it's technically true that this station does have two 350kW and four 150kW connectors, the ElectrifyAmerica stations have redundant connectors on the same station that are there only for convenience to support vehicles with different charge port locations. They are not actually simultaneously usable, so I don't count those as separate connectors.
As for the change from Electrify America to EVolveNY, while the site is sponsored by EVolveNY, the underlying network that manages the site is actually Electrify America. EVolveNY does not have its own network per se, but utilize other networks like EA, Greenlots and EVconnect to manage fast chargers in NY.